Pregunta 1 de 5
When an owner records a Notice of Completion, the direct contractor's deadline to record a mechanics lien is shortened to how many days from the recording date?
Ver la respuesta
Respuesta: B. 60 days
A recorded Notice of Completion shortens the lien-recording window from the standard 90 days. The direct contractor then has 60 days from the recording (b), while subcontractors have 30 days. (a) 30 days is the subcontractor's period, not the direct contractor's. (c) 90 days is the period only when no notice is recorded. (d) 120 days is not a lien deadline. Why it matters: a direct contractor who waits past 60 days after a recorded Notice of Completion loses the lien.